Heat Shrink Packing Machine Installation Instructions

Heat shrink  Packing Machine

Heat Shrink Packing Machine
Installation Instructions

1. Heat shrink packaging machine consumes a lot of power, so the power input power must be greater than the contraction machine name on the standard power, otherwise easy to burn the line or electrical components.
3. Each machine is shipped with a cable connected to the power supply, the end of the head lead part with a power supply identification symbol, must be properly connected, illegal operation may lead to electric shock.
4. When the machine specified voltage of three-phase 380V power supply, must simultaneously enter the standard three-phase four-wire system, otherwise the machine will not work properly, and very easy to burn internal electrical components.
5. Heat shrink wrapping machine must be installed horizontally, otherwise it will shorten the service life of the electric tube. For a network-carried machine, its tilt installation will cause the conveyor belt to deviate from the center.
6. The continuous use of the machine for more than three months, the contraction chamber should be the temperature-resistant wire inspection, according to its aging degree, the replacement.
7. The machine work, the operator's palm and other parts are not allowed to contact with the machine's operation, especially the internal temperature of the contraction chamber is very high, very easy to scald.
8. The packaging work, should be closed first heating switch, so that the conveyor motor and blower motor to continue to run for about 10 minutes, and then cut off the entire power supply.

More information about the machine,please contact sherry@machinehall.com

Leave Message

Number Change